Tinubu orders clearance of more than 300 stranded power containers

· · 3 minutes read
Tinubu orders clearance of more than 300 stranded power containers The Africans Time © theafricanstime.com
Tinubu orders clearance of more than 300 stranded power containers © theafricanstime.com
President Bola Ahmed Tinubu has directed officials to clear more than 300 containers of electricity equipment held at Nigerian ports for 14 to 20 years. The equipment will be assessed for possible use in power projects.

The Federal Government has paid ₦1.23 trillion of an estimated ₦3.3 trillion owed to gas suppliers and other power-sector stakeholders, Power Minister Olasunkanmi Tegbe said at a Federal Executive Council briefing at the State House in Abuja on 28 October 2026. The payments were made through bonds under the Presidential Power Sector Debt Reduction Programme. Tegbe said outstanding liabilities had contributed to difficulties securing adequate gas supplies for generating companies, affecting liquidity across the electricity value chain. He said the government intended to complete the payments while preventing new debts from accumulating.

At the same briefing, Tegbe said President Bola Ahmed Tinubu had directed the Ministry of Power to work with the Nigerian Ports Authority and the Nigeria Customs Service to clear more than 300 containers of electricity equipment stranded at Nigerian ports for between 14 and 20 years. Unpaid port charges and unresolved customs procedures have kept the cargo there. The minister said inter-agency clearing costs could be addressed through netting arrangements between government agencies. The order directs agencies to resolve the port and customs barriers; the equipment is to be inspected after release before any decision on its use. TVC News reported Tegbe’s announcement.

Equipment must be checked before deployment

The clearance will not mean every item can be used. Technical experts are to inspect the containers and assess whether the equipment remains serviceable after prolonged storage. They will also determine which items are obsolete or unusable. Equipment found suitable may be assigned to ongoing electricity projects, while obsolete material is to be disposed of appropriately, Tegbe said, as Punch reported.

The stalled cargo contrasts with equipment moving for other infrastructure projects, including a separate Lamu refinery shipment reported as arriving at the Port of Lamu.

Grid expansion depends on delivery

The government’s proposed East and West Super Grid projects are intended to raise Nigeria’s transmission capacity from approximately 5,000 megawatts to 19,000MW within two years, with the aim of accommodating more than 13,000MW of available generation capacity. President Tinubu has approved procurement for the initiative, which is designed to reinforce transmission corridors across the country. Nigerian NewsDirect reported the capacity targets. Tegbe also said transmission projects had been approved in Abuja and Lagos. Another is planned along the Lagos-Shagamu corridor. They include new lines and three 300MVA transformers at Ikeja West Transmission Substation.

Tegbe reported that construction had begun on a new National Control Centre in Osogbo, Osun State, to replace a 64-year-old legacy facility. He also said the government was working to energise completed substations in Kano and Katsina, as well as those in Bauchi and Gombe.

Topics: Climate & Energy Power & Electricity #Nigeria #Abuja #Lagos #Bola Tinubu