Aquaterra Energy completes first phase of Nigerian offshore platform

· · 2 minutes read
Aquaterra Energy completes first phase of Nigerian offshore platform The Africans Time © theafricanstime.com
Aquaterra Energy completes first phase of Nigerian offshore platform © theafricanstime.com
The six-month phase delivered a subsea template for Emadeb Energy, designed to let drilling begin before fabrication of the rest of the platform is complete.

The subsea template is designed to let drilling begin while the rest of the platform is still being fabricated. Aquaterra Energy offshore developments business-unit leader Edward Betts said the template-first sequence would allow drilling to start before the platform is complete.

Aquaterra Energy has completed the first phase of an offshore platform project for Emadeb Energy, an indigenous Nigerian oil and gas company. As reported on 26 October 2026, the phase took six months and covered the template’s design and fabrication. Aquaterra and Emadeb expect the full development programme to take approximately 15 months, from engineering work through final platform installation, with fabrication and drilling included in that schedule, as World Oil reported.

Drilling ahead of platform installation

The project is being delivered in two stages. Installation of the full platform structure over the completed wellheads is targeted for later in 2026, while work on the remaining structure continues at a Nigerian yard. The overall development is expected to take approximately 15 months, from engineering through final installation, including fabrication and drilling.

The conductor-supported platform will host wellheads and route production to a nearby mobile offshore production unit (MOPU), where it will be processed before export. The subsea template provides access to the wells, allowing drilling to begin before installation of the full platform structure. Aquaterra is providing well-access products and offshore-development services under its contract with Emadeb, information from Oilfield Technology.

Aquaterra adapted elements of its existing Sea Swift platform designs and simplified the topside configuration to reduce build complexity and engineering lead times. Betts said adapting the designs and working closely with Emadeb helped keep the project moving. Fabrication of the remaining structure is progressing at a Nigerian yard. Chevron’s Aseng gas project in Equatorial Guinea has a different stated key stage: first gas is targeted for 2028.

Topics: Infrastructure Oil & Gas #Nigeria #Crude oil