May figures cited by Signwl chief executive Sarah Rees put the cost of renting an Nvidia H100 GPU in Africa at about $13.55 an hour, against a global average of $7.32. That is an 85% premium, driven by limited supply and high energy costs.
The price gap points to a wider constraint for African AI developers: local projects can rely on infrastructure located on the continent but owned or operated by foreign companies. Who controls the technology and retains value from its use remains central to the debate.
Local models depend on external computing
Nigeria's N-ATLAS language model supports Yoruba, Hausa, Igbo and Nigerian-accented English. Unveiled at the United Nations General Assembly in September 2025, it was developed with Lagos-based start-up Awarri. TechCabal reported that Awarri uses Amazon Web Services and Google Cloud for computing. The same reliance on external cloud platforms has featured in an earlier sovereign AI report.
South Africa's Lelapa AI developed InkubaLM, described as the continent's first multilingual small language model, using computing credits from Microsoft's AI for Good Lab. The company says it reduced the model's size by up to 75% without sacrificing performance. Chief executive Pelonomi Moiloa said building lean was necessary "because we must make things work under constraint."
Africa has about 18% of the world's population but less than 1% of global data centre capacity, according to industry estimates cited by the World Economic Forum. Xalam Analytics managing partner Guy Zibi estimates that the continent accounts for about 0.2% of global AI computing capacity. An industry overview puts Africa's share of global data-centre capacity at about 0.6%, with 220 to 230 facilities across 38 countries, concentrated mainly in South Africa, Egypt, Kenya and Nigeria. The Africa Data Centres Association estimates 360 megawatts of active capacity, 238 MW under construction and 656 MW planned. The five largest African markets together have less than 500 MW of installed capacity, compared with about 800 MW in France in 2024, according to The World of AI's overview.
Electricity availability and reliability remain major constraints on data-centre expansion. Africa has substantial solar resources: Strategic Gears estimates the continent has about 60% of the world's best solar resources, but accounts for only 1% of installed solar capacity and less than 2% of global clean-energy investment. One technical estimate puts Africa's solar potential at about 7,900 GW if one percent of its land area were used. Those resources alone cannot provide continuous power for data centres. Transmission, storage and grid connections are also needed, as outlined in Strategic Gears' analysis.
Ownership adds another layer of dependence. South Africa's Teraco has been majority-owned by US-based Digital Realty since 2022, after a transaction that valued the business at about $3.5bn. Digital Realty also acquired Kenya's iColo and Nigeria's Medallion. US-based Equinix expanded its African operations through its $320m acquisition of MainOne's West African data centre business. Digital Realty's international platform spans more than 300 facilities in over 50 metropolitan areas across more than 25 countries. Teraco provides vendor-neutral colocation and interconnection services in sub-Saharan Africa. Its energy strategy includes efforts to increase renewable-power use, as reported by ITWeb.
Efforts are under way to build locally owned capacity. Cassava Technologies launched an Nvidia-powered AI factory in South Africa in March, with plans to expand into Nigeria, Kenya, Egypt and Morocco. It has indicated plans to deploy between 12,000 and 13,000 GPUs across its markets and develop a 20-megawatt facility in Johannesburg. The processors still come from Nvidia, a US manufacturer that dominates the market for high-end AI chips.
Investment and control remain unresolved
Kenya's proposed data centre at Olkaria shows how infrastructure plans intersect with national energy capacity. Abu Dhabi-based G42 and Microsoft announced the $1bn project in 2024 to support an Azure cloud region for East Africa, powered by geothermal energy. At GITEX Kenya, Invest Kenya deal room director Sandy Okoth said the proposal had grown from a 100-megawatt pilot to a potential one-gigawatt development.
Kenya generates about 3,000 megawatts of electricity and has peak demand of roughly 2,400 megawatts. Okoth said the proposed centre would use more than half of the country's available generation capacity. He also questioned government guarantees sought by G42, arguing they could shift private investment risks to Kenyan taxpayers. Kenyan officials told Al Jazeera in June that discussions were continuing; the report does not establish the project's current status.
The labour behind AI is part of the value chain, too. Data Labelers Association president Joan Kinyua represents about 1,100 Kenyan workers who tag images, transcribe audio and moderate content used to train AI systems. "The workers power all these technological advancements, but they're paid peanuts," Kinyua told Computer Weekly when the association was launched.
Kenyan content moderators working on projects for Meta and OpenAI through outsourcing firms have reportedly earned between $1.46 and $3.74 an hour, according to Business Daily. In April, Sama announced more than 1,000 job cuts in Nairobi after its contract with Meta ended. Kenya's draft policy proposes benchmarking pay for data annotation, content moderation and AI evaluation against international rates. It would also require employers to disclose remuneration structures.