Khazna Data Centers has 30 live data centres and 673MW of capacity across its portfolio. It is also building Stargate UAE, a planned 1GW AI cluster within the proposed 5GW UAE–US AI Campus in Abu Dhabi. G42, OpenAI, Oracle, NVIDIA, SoftBank Group and Cisco announced Stargate UAE in May 2025. The campus is planned to combine nuclear, solar and gas generation, with access to computing resources overseen by the US and UAE governments and intended for US hyperscalers and approved cloud providers.
The first 200MW of Stargate UAE is targeted for 2026. The UAE’s ambassador to the US, Yousef Al Otaiba, described the 5GW campus as a project built with American partners and powered by American chips in a letter to the business community. That scale puts Khazna CEO Hassan Alnaqbi at the centre of one of the region’s largest planned data centre expansions.
AI campuses drive the largest capacity plans
Khazna has six data centre construction projects under way to LEED standards. It is delivering 200MW of additional capacity for Microsoft and G42, alongside a 100MW AI-optimised campus in Ajman. Its first Saudi site is a 200MW facility in Dammam, part of a plan to add more than 1GW in the country by 2030. G42 owns Khazna; MGX and Silver Lake are minority investors.
HUMAIN is assembling another major build-out. Since the PIF-owned AI company launched in May 2025, CEO Tareq Amin has lined up AWS, AMD, Qualcomm, xAI, DataVolt and center3 as partners. Its first 100MW campuses in Riyadh and Dammam were slated for the second quarter of 2026, within a plan for around 6GW over the next decade. Amin has set phased capacity targets of 1.7GW in 2027, around 3GW by 2030 and approximately 6GW by 2034, as he told Sharikat Mubasher. HUMAIN has secured 211 land plots.
Amin previously led Aramco Digital and Rakuten Symphony. HUMAIN’s capacity plans also depend on other operators: at NEOM’s Oxagon, DataVolt has started construction on a campus whose first phase is planned at 360MW, within a longer-term 1.5GW development.
DataVolt CEO Rajit Nanda founded the Vision Invest-owned developer in 2023, after serving as Chief Investment Officer at ACWA Power. HUMAIN is taking the first 100MW at Oxagon, due in 2028, within the campus plan. In Riyadh, HUMAIN anchors more than 80% of DataVolt’s US$500m Riyadh East site, which is targeting financial close. Separately, HUMAIN has invited contractors to bid for a 100MW AI data centre in the Al-Saad area of Riyadh, with an estimated contract value of US$1bn. The tender schedule set a bid deadline of 8 November 2026, with construction expected to start in January 2027; its first and second phases were scheduled for October 2028 and January 2029.
Capacity targets are still targets. The distinction matters across projects that span operational sites, construction and facilities awaiting financial close.
Regional operators expand across African markets
In South Africa, Teraco CEO Jan Hnizdo leads a business that has grown from 500kW in a Cape Town basement in 2008 to roughly 190MW of critical load across Johannesburg, Cape Town and Durban. JB7 is due in 2026 and is expected to lift the total to 228MW. Teraco also operates NAPAfrica, Africa’s largest internet exchange.
Digital Realty raised its stake in Teraco to 77% this year by buying 16% from minority holders for about US$650m, after its 2022 majority purchase at a US$3.5bn valuation. Teraco is building a 120MW solar PV plant to supply its sites and has signed its first wind power purchase agreement. JB5, a 30MW hyperscale build completed last year, uses zero-water cooling.
Africa Data Centres CEO Adil El Youssefi leads facilities in Johannesburg, Cape Town, Nairobi and Lagos, serving more than 400 enterprise and hyperscale customers. He also leads Co-location at parent Cassava Technologies, having joined the group in 2017 to run its Kenyan operations.
STANLIB, the Standard Bank Group asset manager, won unconditional competition approval earlier this year for joint control of the South African business. The deal is funding AI-ready expansion in Johannesburg and Cape Town, where the campuses also host Cassava’s NVIDIA-based AI factory. Africa Data Centres was founded in 2018 and is headquartered in Johannesburg.
Open Access Data Centres (OADC) is extending its footprint across South Africa, Nigeria and the DRC. CEO Dr Ayotunde Coker leads the WIOCC subsidiary, which closed its purchase of seven NTT DATA sites at the end of 2025 and is leasing them back to NTT DATA. The transaction lifted South African capacity above 25MW.
A US$240m expansion backed by IFC and Proparco is expected to take OADC’s Lekki campus in Lagos from 1.5MW to 24MW by 2027. Coker previously led Rack Centre. In an exclusive interview with Data Centre Magazine, he said sustainability is something the company takes “very seriously”.
Kenya’s iXAfrica Data Centres is developing capacity around Nairobi. CEO Snehar Shah leads what the company bills as East Africa’s largest hyperscale-ready facility, backed by US$50m from majority investor Helios Investment Partners. NBOX1, its 4.5MW first phase, is part of a planned 22.5MW Nairobi Campus.
Oracle selected iXAfrica in January to host its Nairobi cloud region, with Safaricom as a go-to-market partner. Safaricom is also the subject of a Kenyan court appeal over Vodacom’s proposed bid. A reported Rand Merchant Bank debt package of up to US$200m supports expansion, with NBOX1.2 (18MW) and a planned 53MW Tilisi campus to follow.
iXAfrica was founded in 2021 and is headquartered in Nairobi. Its projects combine a cloud-region customer with planned campus growth, while the reported debt package remains a financing detail rather than evidence that all expansion capacity is operational.
Established operators and new platforms
Fahad AlHajeri runs center3, stc Group’s data centre and network infrastructure business. The Riyadh-headquartered company, founded in 2022, has pledged US$10bn on top of the US$3bn already spent, with targets of 300MW by 2027 and 1GW by 2030.
Oracle and Huawei host their Saudi cloud regions in center3 facilities. In December, center3 announced a joint venture with HUMAIN for up to 1GW of AI capacity, starting at 250MW.
Equinix’s regional footprint spans six facilities across the UAE and Oman. Kamel Tawil, Managing Director for MENA, has led the operator’s regional growth since 2020 after 18 years at Oracle. Its sites include DX3 in Dubai and SN1 in Salalah, built with Omantel as a subsea cable landing site.
Equinix has announced a US$1bn, 100MW site in Saudi Arabia. The company was founded in 1998 and is headquartered in Redwood City, California; Group CEO Adaire Fox-Martin leads the wider business.
Gulf Data Hub CEO Tarek Al Ashram oversees about 40MW of live capacity in the UAE and Saudi Arabia, with around 90MW under construction. A KKR partnership backs more than US$5bn of investment. The company was founded in 2012 and is headquartered in Dubai.
Egypt is planned under a 2023 memorandum with Elsewedy Data Centers. In August, Al Ashram also backed MTN’s Africa Data Hub venture, which is targeting 150MW in South Africa and Nigeria. He did so through his own investment platform rather than Gulf Data Hub.